RESTORATION 2012 - 2014

<<Previous   Next >>

First 1 2 3 Last

In 2011 the SCCS was approached by Paulton Parish Council and asked to suggest a way forward to improve the area which formed the Western terminus of the S.C.C. and included Timsbury Basin, Paulton Basin and Paulton Dry Dock. It soon became apparent that the landowners in this area were in favour of restoring the canal, although this had seemed an impossible dream. In Spring of 2012, the SCCS began restoration work with considerable assistance from the landowners.

January 2012

Paulton Dry Dock

Drainage work began

March 2012

Work party rained off

April 2012

Paulton Dry Dock

A wall was discovered during drainage work

October 2012

Paulton Dry Dock

Water level lowered enough to allow SCCS and WRG to undertake major clearance work

November 2012

Work party snowed off

Site then flooded

April 2013

Paulton Dry Dock

A collapsed culvert was discovered in the SE corner of the Dry Dock. It was cleared out and rebuilt by members of the SCCS, WRG and local landowners.

April 2013

Paulton Dry Dock

Archæological dig followed by...

Excavation with a mini-digger to reveal the full extent of the basin, 30ft x 83ft, making this almost certainly the largest canal dry dock in Britain.

October 2013

Paulton Dry Dock

Culvert completed

Stop plank point repairs begun.

December 2013

Paulton Dry Dock

Stop plank point completed

Landowners begin repairing the stone arch over the Dry Dock entrance

April 2014

Paulton Dry Dock

A large excavator begins clearing earth from the Dry Dock


Photograph: David Fearns

April 2014

Paulton Dry Dock

The full size of the dock is revealed


Photograph: David Fearns

August 2014

Paulton Dry Dock

The Dry Dock arch abutments have been rebuilt ready to receive the arch

August 2014

Paulton Dry Dock

The wooden centring is being prepared ready to support the Dry Dock arch stones during construction

September 2014

Terminus Bridge

Digging out the infill

September 2014

Terminus Bridge

Uncovering the stop plank point

September 2014

Withy Mills Batch

The location of the Withy Mills stop plank point discovered

October 2014

Dry Dock Arch

Reconstruction begun


Map of the S.C.C. between Paulton and Radford

October 2014

Withy Mills Narrows
to
Dunford West Narrows

Canal dug out

October 2014

Dunford West Narrows

dug out and stop plank groove revealed

October 2014

Withy Mills Narrows

WRG begin rebuilding the stonework

November 2014

Radford Mill Farm

Digging out in progress

November 2014

Terminus Bridge

Canal cleared from drainage culvert to bridge narrows

December 2014

West of Withy Mills

Work begins to build up towpath and waterproof 'puddling clay' to correct level.

December 2014

Radford Mill Farm

Radford Colliery Wharf and the footings of Dunford Bridge uncovered

December 2014

West of Withy Mills

After days of rain the canal is beginning to fill from springs in the field above

December 2014

West of Withy Mills

Work is temporarily suspended as conditions become too boggy for the digger to work safely